Project description
The project activities will install landfill gas extraction
equipment and utilize the recovered gas to generate electricity at
Mianyang landfill in Sichuan Province, China.
The project activity will use state of the art horizontal piping
systems combined with rainfall management technics including
drainage and erosion control and daily cover to maximise landfill
gas extraction efficiency.
The applied methodology is ACM0001 / Version 05 "Consolidated
baseline methodology for landfill gas project activities".
The project is a normal scale CDM project activity.
Crediting period is 10 years fixed and expected to start from
01/01/2008.
Estimated annual average emission reduction is 167,387t-CO2.
Project design
document (PDD)
Period for comments: 02 June to 01 July 2007 no comments
received.