Clean Development Mechanism Projects
Project Title
Qinghai Golmud Yixiantian 8MW Small Scale Hydropower Project
Country
China
Project description
The project involves the installation of 2 hydro turbines, each
of which has a capacity of 4MW, reaching a total install capacity
of 8 MW at Golmud City of Haixi Mongolian and Tibetan Autonomous
Prefecture in Qinghai Province, China.
Supplying power generated by hydrological resources of the
Naijin River to Northwest China Grid can reduce the emission of
greenhouse gases to the atmosphere.
The applied methodology is AMS I D / Version 12 "Grid connected
renewable electricity generation".
The project is a small scale CDM project activity.
First renewable crediting period is 7 years and expected to start
from 01/01/2008.
Estimated annual average emission reduction is
25,619t-CO2.
Project
Design Document (PDD)
Period for comments was 03 November 2007 - 02 December 2007.
No comments received.