Clean Development Mechanism Projects
Project Title
Yunnan Huaguohe 7.5MW Hydroelectric Project
Country
China
Project description
Yunnan Huaguohe 7.5MW Hydroelectric Project is to utilize the
hydrological resource in run-of-river scheme to generate zero
carbon emission electricity for the South China Power Grid (SCPG).
The Project will generate certified emission reductions (CERs) by
displacing electricity generation from grid connected fossil
fuel-fired power plants that would otherwise be generating
electricity needed.
The total installed capacity of the Project is 7.5MW, including two
run-of-river hydropower plants-Zhengba hydropower plant, and
Muguashu hydropower plant with installed capacity of 5MW and 2.5MW
respectively. It is estimated that an estimated annual power output
of 33,536 MWh that will be delivered to the SCPG.The emission
reduction resulted from the replacement of thermal power is
expected to be 28,283tCO2e per year.
Renewable crediting period of 7 years first crediting period is
chosen and expected starting date is 01/10/2008.
The applied methodology is The simplified baseline and monitoring
methodology AMS I.D., version 13, 14 December 2007, "Grid Connected
Renewable Energy Generation"
Project Design Document (PDD)
Period for comments: Was the 17th June to 16th July 2008.
No comments were received.