Challenge
Within a six‑month period, two identical diesel alternator engines on one of the client’s LNGC vessels suffered catastrophic failure. While no injuries occurred, the loss of generating capacity created a significant operational risk for the vessel’s DFDE power plant. Beyond the immediate schedule impact, the financial cost of repairs ran into millions of dollars.
Although the Original Equipment Manufacturer (OEM) had begun investigating and repairing the units, the client needed an independent root cause analysis to understand the underlying technical issues and to prevent further potentially harmful incidents.
Solution
Lloyd’s Register’s (LR) Advisory Technical & Failure Investigation (TFI) team conducted an impartial RCA combining onboard inspection, laboratory‑based metallurgical and chemical analysis, and a thorough technical review of operational, maintenance and design documentation.
This provided a clear evidence base to understand what caused the repeated failures.
Approach taken
A TFI specialist attended the vessel to inspect the failed engines and engage with the ship’s engineering staff and OEM personnel. Components from the second failure were removed and shipped to TFI’s UK laboratory for detailed analysis, while parts from the first failure were examined at the OEM’s facility. The team reviewed operating hours, service reports, maintenance and overhaul records, alarm and shutdown histories, cooling water and lube oil analysis, monitoring system data and OEM design documentation.
Key activities and outpouts
- Onboard investigation and identification of affected components
- Removal and laboratory analysis of failed parts
- Inspection of OEM‑handled components from the first failure
- Comparative assessment of sister‑vessel engine condition
- Review of operational records and laboratory data
- Delivery of a detailed technical RCA report with actionable recommendations.
Key customer benefits
- Better understanding of factors contributing to engine failure
- Greater confidence in OEM maintenance and inspection requirements
- Reduced exposure to high‑cost repairs
- Lower risk of operational disruption.
Project outcome
LR Advisory’s TFI team provided a clear, evidence‑based explanation of the probable root cause, supported by inspection findings and metallurgical results. The conclusions allowed the client to implement focused mitigation actions, significantly reducing the likelihood of recurrence and enhancing operational reliability.
Impact on customer's business & operations
By identifying the underlying issues, the client was able to move from reactive repair to planned intervention. This strengthened power‑plant reliability, provided greater cost predictability, improved safety of crew working conditions and reduced the risk of further unplanned interruptions.
Conclusion
The investigation provided a robust technical basis for corrective actions and informed updates to OEM inspection routines and onboard maintenance procedures. This enhanced control over engine operating condition and supported long‑term power‑plant reliability.
Other Applications
This approach can be applied to machinery failure investigations across marine and land‑based assets where independent technical assessment is required.